If you live in Chelan you might have noticed that the build site has been quiet lately, and that is because we have paused construction. Here’s everything you need to know, as well as how you can help keep this project moving forward: The Reason for the Pause Our steel…
Site Update
Check out the latest progress on site at the Community Center at Lake Chelan! https://www.youtube.com/watch?v=SUdndj5PPrA Video Courtesy of Rimmer & Roeter Construction
Site Update
This week on-site: Concrete Footings and Foundation are pouring this week, and some gravel is being laid out for parking lot. This month: Final review stages for overall building permit are processing through the City of Chelan.
Children’s play area
Here’s a sneak peek of the “John and Helen Horan” Playground! Parents can grab a drink from The Vine Coffee and socialize while they watch their kids play.
power, water, sewer
Construction is now underway with Power, Water, and Sewer connections beginning on site. Retaining walls, footings, and under slabs will be the next steps later this summer. We are thrilled to have ordered the first phase of steel for the main building from Butler Manufacturing. We have a target opening…
grading and leveling
Thank you Richard Uhlhorn Photograpy for taking pictures of the progress!! It is so exciting to see the transformation!!
DIRT IS MOVING!!
Construction has started! Heavy equipment is in motion with grading and leveling progressing on site today. Thank you to Rimmer & Roeter Construction, Torrence Engineering, and Complete Design for driving this project forward. We are thrilled to have you on our team!
Grading Permit submitted
The grading permit application was submitted to the City of Chelan last week with effort moving toward ground breaking. Permits have been issuing in the 3-6 week timeframe. Earthwork is set to commence upon approval of grading permit. Watch for signs of Rimmer & Roeter Construction!
conditional use permit application decision approved
Seven Acres Foundation received the Notice of Decision today for approval of a conditional use permit by City of Chelan Land Use Hearing Examiner, CUP #2020-08 and SEPA #2020-06, for the Community Center at Lake Chelan. Next step: Submit grading permit application to move toward ground breaking, earthwork, and infrastructure.
NAMES FAMILY FOUNDATION DONATES $500,000!
The Community Center at Lake Chelan receives major donation from Names Family Foundation! Erin Shagran, Treasurer of the Names Family Foundation, said granting this award was a relatively easy decision to make. “Although we are based in the Puget Sound area, our family has deep roots and very close ties…